Construction of primary water supply network Poriječani, reconstruction of reservoir “Pertac” and water spring “Vrutak”.

Unioninvest d.d. as the main contractor, performed the contracted works promptly, professionally, with high quality and within the given deadlines.

Key project data:
Identification number: BA-EBRD-VisokoWSS-W-02/18
Subject: Construction of the Poriječani primary water supply network, reconstruction of the Pertac reservoir and the Vrutak spring
Employer: JKP Visoko d.o.o. Visoko, Bosnia and Herzegovina
Contract duration: 300 days
Signing of the contract, date: 15.02.2019.
Contract Price: 2,682,228.99 KM (1,371,401.90€)

Ongoing projects

Waste water treatment plant Prozor-Rama

Key project data: Identification number: 20060272-s040. Subject: Design and construction of wastewater treatment plant Prozor Rama (PE 3,000+3,000). Employer: Municipality of Prozor Rama, Bosnia and Herzegovina. Contract duration: 2 years. Signing of the contract, date: 16.07.2019. Contract Price: 3,547,725.99 KM (1,813,923.50 €)

More info »

Waste water treatment plant Bosanski Petrovac

Key project data: Identification number: 01/1-1-25-7482-UP-1/17
Subject: Design and construction of a wastewater treatment plant in Bosanski Petrovac (PE 5,000). Employer: Municipality of Bosanski Petrovac, Bosnia and Herzegovina. Contract duration: 2 years. Signing of the contract, date: 30.10.2018. Contract Price: 2,929,057.32 KM (1,497,603.23 €)

More info »