Performing works on the Depot facility at the Srebrenica-Potočari Memorial Center

Project: Execution of works on the Depot facility at the Srebrenica-Potočari Memorial Center

This involves the construction of a depot for storing biological materials, items, and personal clothing of genocide victims, along with necessary infrastructure.

Investors: Srebrenica-Potočari Memorial Center and Catholic Relief Services

Supervision: Sarajevo Canton Construction Institute

Contractor: Unioninvest d.d. Sarajevo

Designer: Vizija d.o.o. Sarajevo

Project value: 1.421 840,28 BAM (725.000,00 €)

Ongoing projects

PS Krivoglavci 1 i 2

Investor/Contractor: Municipality of Vogošća, KJKP “ViK” d.o.o. SarajevoEngineer: KS Construction InstituteProject value: 717,700.00 BAMPS Krivoglavci 1As part of the activities to solve the problem of

More info »

Waste water treatment plant Prozor-Rama

Key project data: Identification number: 20060272-s040. Subject: Design and construction of wastewater treatment plant Prozor Rama (PE 3,000+3,000). Employer: Municipality of Prozor Rama, Bosnia and Herzegovina. Contract duration: 2 years. Signing of the contract, date: 16.07.2019. Contract Price: 3,547,725.99 KM (1,813,923.50 €)

More info »
Shopping Basket