«Prim.dr. Abdulah Nakaš», Sarajevo
Public Institution General Hospital «Prim.dr. Abdulah Nakaš», Sarajevo, dating from the 19th century, with specialized-consultative service within the more than 20 primary and oriented medical disciplines, provides its customers high standards of quality and safety, and the possibility of hospitalization as well as planned surgeries.
Within complete reconstruction of the steam heat substations in the General Hospital “Prim. Dr. Abdulah Nakas” Sarajevo, all elements of the old substation have been dismantled and have been built compact steam “Danfoss” substations made of modules, which after the connection, constitute a single entity.
Five reconstructed steam substations have capacity to fully meet the needs for heating, hot water consumables and thermal disinfection of water:
P 23 – O I | capacity | 1.100 kW |
P 23 – O II | capacity | 550 kW |
P 25 – O I | capacity | 1.500 kW |
P 301 – O I | capacity | 500 kW |
P1203 – O I | capacity | 1.200 kW |
Working of the embedded substation is fully remote monitored and enables monitoring and management from a single location.
The connection of quality components, rational composed , correctly embedded and connected in a compact system provided conditions that are necessary for operation of these types of facilities.
Basic information:
Total contract value: 776.617,94 BAM (397.078,45 €)
Investor: Public Institution General Hospital «Prim.dr. Abdulah Nakaš», Sarajevo
Location / Address: Sarajevo,B&H
Period: February 2014 – November 2014