Vrsenje-strucnog-nadzora-nad-objektima-Pretis-Vitezit-I-Binas-UNDP-Bosnia-Herzegovina-2

Technical supervision of buildings “Pretis”, “Vitezit” & “Binas”; UNDP Bosnia & Herzegovina

By signing a contract with UNDP, Unioninvest had an obligation to supervise the construction and craft works, electrical works (strong and weak stream), hydro and mechanical works on the following facilities:
 “Pretis” Vogošća
 “Vitezit” Knight
“Binas” Bugojno
These facilities are for production of products for special purposes (military products,  weapons, ammunition, etc.)

Basic information:

Total value: 29.500,00 BAM (15.083,00 €)
Investor: UNDP B&H
Period: May 2010 – July 2010
Location: The area of Bosnia and Herzegovina (Vogošća, Vitez i Bugojno)

INVESTOR CERTIFICATE LINK

unioninvest-thumbnail

Other projects

TECHNICAL DOCUMENTATION, PRELIMINARY AND DETAILED DESIGN; POST OFFICE 75260 KALESIJA – ROOF REPAIRS, FACADE AND AIR CONDITIONING

Investor: BH Post doo Sarajevo, Tuzla Post center
Total value: 3,400.00 BAM (€ 1,740.00)
Period: May 2012 

TECHNICAL DOCUMENTATION, PRELIMINARY AND DETAILED DESIGN; POST OFFICE 75101 TUZLA – VENTILATION

Investor: BH Post doo Sarajevo, Tuzla Post center
Total value: 3.861,00 BAM (1.974,00 €)
Period: November 2011

DESIGN for ELECTRICAL INSTALLATIONS; new schedule of working machines in the facility “Žica” dd Sarajevo

Investor: “Žica” dd Sarajevo
Total value: 4,680.00 BAM (€ 2,390.00)
Period: 2011

CONSULTING SERVICES, MANAGING THE CONSTRUCTION OF THE BUILDING TO ITS FINAL STAGES; RR ENGINEERING LTD. PODGORICA,MONTENEGRO

Investor: RR Engineering Ltd. Podgorica
The total value of 235,000.00 BAM (€ 120,154.00)
Period: May 2010 – September 2010

Proizvodni-i-skladisni-objekat-u-Binjezevu-industrijska-zona-Sarajevo-3

Manufacturing and warehouse facility in Binjezevo- indsutry zone of Sarajevo

At the specified location investor plans to build office-production and storage facilities. The construction would be implemented in phases as following;

In the first phase, in the southern part of the parcel, construction of office and warehouse facility with two parallely located halls, measuring 40.60 m X 12.70 m, and between the sheltered manipulative plateau with dimensions of 30.00mX9.40 m, is planned.  In the wester hall a boiler room with height h = 470cm is located, walled with bricks and finally plastered. At the bottom of the plateau, towards the river Zujevina a storage building with changing rooms and toilets, staff kitchenette and two offices is planned.

All vehicular access and pedestrian facilities are provided through manipulative plateau, and this is an internal traffic along the western border of the area, linked to industrial roads in the north..

Around the area a wire fencing with entrance gate to connection with industrial road is designed.