Within the project were dismantled two of the four existing boilers.
The other two existing boilers which operate with extra light oil EL (type Viessmann 2.500 Mcal / h and Viessmann 3.000mcal / h) were repaired and put into proper condition , also repaired and reconstructed all mechanical installations, including the reconstruction of the ventilation system .
Two new boilers (low pressure steam boiler p = 0.5 bar , with Q = 5 t / h , the power of 3.300 kW ) combined with new burners for operation with natural gas / extra light oil were built.
As an additional security measure, in the boiler room has been installed a new system for gas detection in Ex version, as well as the connecting the new fire alarm system with the existing one.
Basic information:
Value of the contract : 862.578,11 BAM ( € 441.030 )
Client: Ministry of Finance and Treasury B&H
Location / Address : Sarajevo
Period : March 2011 – October 2011