Sjediste-Raiffeisen-banke-dd-BiH-Sarajevo-3

Headquarters of Raiffeisen bank dd B&H, Sarajevo

Unioninvest dd Sarajevo and Raiffeisen Bank dd B&H reached an Agreement on Sale, Purchase, Development and Construction of the Raiffeisen Bank Headquarters Project in Sarajevo.

Unioninvest completely developed this property for Raiffeisen Bank HQ, being also a  General contractor for the Turn-key construction works on the headquarters Raiffeisen Bank dd B&H in Sarajevo, consisting of office Building A and office Building B with associated garage space.  

Unioninvest had been coordinating the entire building project with the competent authorities, including obtainment of all Permits necessary for the execution, occupation and operation of the works.  The scope of work aslo included obtainment of the Use Permit together with any and all services and supplies, and all public utilities necessary and useful to operate the building in accordance with its intended use as a bank and office building.

Based on preliminary designs, Unioninvest dd. has developed the main design for all phases of construction as well as the complete „as built“ documentation and all operations and maintenance manuals. 

The building has an up-to date, state of the art, technical systems and standards (European A class building) of air conditioning, heating, electrical, fire and security systems with Building Management system.

Basic information:

Total Value: 61.000.000 BAM (31.188.804,75 €)
Investor: Raiffeisen Bank dd BiH
Area, net: approx 15.600 m2 (Building A) + 8.100 m2 (Building B)
Floor number: 
3S + P + M + 9 + TF – Building A; 
3S + P + 3 + TE – Building B
Location / Address: Quadrant C, Marijin Dvor, Zmaja od Bosne bb street, Sarajevo
Period: September 2006 – September 2010
Professional Supervision: O:SNAP
Few technical details:

Building ABuilding B
Installed electric capacity TS: 2×1.000 kVA in parallel operation Pi=2117kW,Pv=1700kWUPS: 2×275 kVA  in parallel operation Pi=Pv=465kWDEA: 2x 500kVA, Pi=1103kW,Pv=772kWCooling capacity: 1.200 kWBoiler capacity(combined extra light heating oil – natural gas): 1.000 kWInstalled electric capacity TS: 1×1.000 kVA,10(20)/0.42kV, Pi = 1068 kW, Pv = 908 kWUPS: 1×275 kVADEA: 1×500 kVA Boiler capacity (combined extra light heating oil – natural gas): 780 kW

INVESTOR CERTIFICATE LINK
SUPERVISION CERTIFICATE LINK

Poslovni-objekat-A6-zgrada-UN-a-1

Office building A6, the UN building

Unioninvest dd as the owner of the land, the Investor and the General contractor, developed this remarkable office building.

Office building A-6 is designed as a modern business building of high rank and it is a part of a series of office buildings along Vilson promenade forming a unified unit of office buildings for foreign diplomatic – consular and commercial branch offices.

By general concept simple volume is formed and in accordance with the requirements of the clients in functional – organizational sense, can be divided into two or more spatially – functional units.

The building has the most modern technical systems and standards (European A class object) of air conditioning, heating and cooling (HVAC), electrical, fire and security systems.

Unioninvest dd has designed all phases of construction, and supervised the construction of the building.

The building is occupied by agencies of United Nations and Unioninvest is responsible for the management and maintenance of the building.

Basic information:

Total investment: 20,000.000 EUR (€ 10,000.000)
Investor: Unioninvest dd Sarajevo
Area: approximately 7,500 m2
Floor number: 2S + P + 3
Location / Address: Quadrant C, Marijin Dvor,  Zmaja od Bosne bb street, Sarajevo
Period: 24 months, 2010-2013
Professional supervision: NON STOP, Unionivest

Bjelasnica-apartmani-2

Bjelašnica apartments

Unioninvest dd, as an investor, a designer and a general contractor, completely constructed two apartment buildings 14 and 37 on Mountain Bjelasnica, municipality Trnovo, near the ski center, 23 km from the city of Sarajevo.

At the very inaccessible terrain in the period 2005-2006 year, the two buildings were built:

Building 37 and Building 14 of the total gross area: 5.211 m2 (building 37) and 2.456 m2 (building 14).
Each of the buildings have 35 apartments of different sizes. All apartments are south oriented to ski tracks of SKI center Bjelašnica.
Building 37 is a building with a three basements, ground floor, first floor and attic, where the main entrance is situated on the ground floor. On the Basement 3 is garage.
Building 14 is a building with one basement, groundfloor, first and second floor and attic, where the main entrance is situated on the basement floor. Here is designed an open parking lot.
Apartments were built  in accordance with high professional standards.
Each apartment has the final finished interior surfaces, and  fully equipped toilet (cantilevered toilet seats with built-in water tank, standing sink and shower) and kitchen (cooker hood , refrigerator, dishwasher , Ceran stove and oven) .
All used construction materials are of natural origin .
External joinery is made of pine wood and shutters are also wooden .
The floors in the toilet are made with A class ceramic tiles.
Apartments are heated by radiators (gas/electric heating), has hot sanitary water, derived phone connections and cable television .

Basic information:

Land value:504.459 KM
Total investment : 9.923.132,81 KM (5.073.617 €)
Value of civil&crafts works: 4.500.000 BAM
Value of installation works : 2.250.000 BAM
Investor: Unioninvest dd Sarajevo
Building 37 : approx 5.211 m2
Floor number Building 37 : S1 + S2 + S3 + P + 1 + M
Building 14 : approx 2.456 m2
Floor number : S1 + P + 2 + M
Location / Address: Mountain Bjelasnica , Municipality Trnovo , Canton Sarajevo
Period : 12 months , 2005-2006

Aerodrom-revizija-projekata-3

Airport project revision

Revision of Main Design of Expansion of Terminal B, International Airport Sarajevo

In accordance with the Regulation on the Construction Site arrangement, required documentation, and on-site participants (Official Gazette of FBiH 48/09 of 27.07.2012.), Revision of Main Design of  Expansion of Terminal B,  Sarajevo International Airport was made and includes the following design phases:

  • Architecture and Landscaping
  • Construction part
  • Sprinkler installation
  • Technology of airport transport system
  • Hydroinstallations
  • Mechanical installations 
  • Electrical installations, weak and strong current

Expansion of the passenger terminal B includes:

  • Construction and expansion of the terminal 1st phase (approximately 10.800 m2 brutto)
  • Modification of existing terminal (approximately 9.000 m2 brutto)
  • Construction of corresponding Landscaping (approximately 10.000 m2 brutto)
  • Construction of all utilities for the Project

Basic information:

Total Value: 29.250,00 BAM (€ 14.955)
Investor:  Sarajevo International Airport 
Period: January 2012 – November 2012

unioninvest-thumbnail

Designing and certification of electrical projects for year 2011; Enterprise for physical and urban planning for city of Zenica

By signing the Framework Agreement Unioninvest has assumed the obligation of the design , inspection and certification of electrical projects for year 2011, according to the requests of the Public Enterprise for Physical and Urban Planning for city Zenica doo Zenica .

During 2011 year was implemented as follows:

  • Inspection and certification of the main project of adaptation and extension of the City sports hall in Zavidovici
  • Inspection and certification of the main project of individual residential building in Gornja Gracanica , street Bare no.40
  • Inspection and certification of the main project of CATV – cable television Nemila
  • Inspection and certification of the main project of wiring for ECO house at Smetovi
  • Inspection and certification of the main project for the construction of cable networks for  Blimišće, Lukovo Polje and Rastopočje, Municipality of Zenica

Basic information:

Total value: A framework agreement was signed in percents
Investor: Public Enterprise for Phisical and Urban Planning for city Zenica doo Zenica .
Period : 2011 years

Vrsenje-strucnog-nadzora-nad-objektima-Pretis-Vitezit-I-Binas-UNDP-Bosnia-Herzegovina-2

Technical supervision of buildings “Pretis”, “Vitezit” & “Binas”; UNDP Bosnia & Herzegovina

By signing a contract with UNDP, Unioninvest had an obligation to supervise the construction and craft works, electrical works (strong and weak stream), hydro and mechanical works on the following facilities:
 “Pretis” Vogošća
 “Vitezit” Knight
“Binas” Bugojno
These facilities are for production of products for special purposes (military products,  weapons, ammunition, etc.)

Basic information:

Total value: 29.500,00 BAM (15.083,00 €)
Investor: UNDP B&H
Period: May 2010 – July 2010
Location: The area of Bosnia and Herzegovina (Vogošća, Vitez i Bugojno)

INVESTOR CERTIFICATE LINK

unioninvest-thumbnail

Other projects

TECHNICAL DOCUMENTATION, PRELIMINARY AND DETAILED DESIGN; POST OFFICE 75260 KALESIJA – ROOF REPAIRS, FACADE AND AIR CONDITIONING

Investor: BH Post doo Sarajevo, Tuzla Post center
Total value: 3,400.00 BAM (€ 1,740.00)
Period: May 2012 

TECHNICAL DOCUMENTATION, PRELIMINARY AND DETAILED DESIGN; POST OFFICE 75101 TUZLA – VENTILATION

Investor: BH Post doo Sarajevo, Tuzla Post center
Total value: 3.861,00 BAM (1.974,00 €)
Period: November 2011

DESIGN for ELECTRICAL INSTALLATIONS; new schedule of working machines in the facility “Žica” dd Sarajevo

Investor: “Žica” dd Sarajevo
Total value: 4,680.00 BAM (€ 2,390.00)
Period: 2011

CONSULTING SERVICES, MANAGING THE CONSTRUCTION OF THE BUILDING TO ITS FINAL STAGES; RR ENGINEERING LTD. PODGORICA,MONTENEGRO

Investor: RR Engineering Ltd. Podgorica
The total value of 235,000.00 BAM (€ 120,154.00)
Period: May 2010 – September 2010

Proizvodni-i-skladisni-objekat-u-Binjezevu-industrijska-zona-Sarajevo-3

Manufacturing and warehouse facility in Binjezevo- indsutry zone of Sarajevo

At the specified location investor plans to build office-production and storage facilities. The construction would be implemented in phases as following;

In the first phase, in the southern part of the parcel, construction of office and warehouse facility with two parallely located halls, measuring 40.60 m X 12.70 m, and between the sheltered manipulative plateau with dimensions of 30.00mX9.40 m, is planned.  In the wester hall a boiler room with height h = 470cm is located, walled with bricks and finally plastered. At the bottom of the plateau, towards the river Zujevina a storage building with changing rooms and toilets, staff kitchenette and two offices is planned.

All vehicular access and pedestrian facilities are provided through manipulative plateau, and this is an internal traffic along the western border of the area, linked to industrial roads in the north..

Around the area a wire fencing with entrance gate to connection with industrial road is designed.

Dom-zdravlja-Novi-Grad-Kumrovec-rekonstrukcija-objekta-1

Health center Novi Grad Kumrovec, reconstruction of the building

Works on aadaptation, partial rehabilitation and upgrading of the building Health Center Novi Grad “Kumrovec” – second phase.

The building of the Health Center Novi Grad, built in 1974, is the largest medical center in Sarajevo, and serves the largest population in the Sarajevo Canton.

Represents the synonym for primary health care of the Sarajevo Canton, and considering that it has suffered significant damage in the previous war activities, with reconstruction performed by Unioninvest, the building will shine in the right light, and very soon open doors for its patients.

The reconstruction, among the other things, includes drafting of new floor and wall coverings, replacing interior doors, upgrading of the third floor to expand dental services, as well as repairs of the roof, and the closure of the passage and an exterior staircase. 

It is also necessary to replace and rehabilitate existing electrical, water and sewage installations, as well as facades and heating installations and landscaping.

Basic information:

Total contract value: 4,129.347,20 BAM (2,111.301,70 €)
Investor: Public Institution Dom Zdravlja Canton Sarajevo
Location / Address: Otoka, Sarajevo
Period: 2015-2016

DIP-patologija-2

Diagnosis and polyclinic, pathology

Supply and installation of central ventilation and air conditioning system – Pathology, including all related mechanical, electrical and civil works in the areas of Clinical Pathology at the third floor and the roof of the Clinical Center building.

Installation includes all the associated installations and equipment, as well as commissioning and proving designed parameters.

Air chamber: Q = 95 kW

Condensation unit Qc= 44kW, Gh = 42 kW, medium freon

Basic information:

Total contract value: 139.906,42 BAM (71.533,00 €)
Investor: Clinical Center University of Sarajevo, KCUS
Location / Address: Ul. Bolnička br.25, Sarajevo
Period: April 2015-ongoing project