Investor: UMNIK Kosovo
Start of construction: July 2002
Completion of construction: April 2003
Value of performed works 1,374,948.50 BAM (€703,000.00)
Work was carried out on the reconstruction of the pumping station with three pumps:
- capacity Q=3×1600 kW,
- engine power N=3×6.3 kV,
- lifting height H= 90 m (NPSH=10 m)